Why Choose Heap Leaching for Oxidized Gold Ore Processing?

Jan 08, 2026 Leave a message

For highly oxidized low grade gold ore, the cost-effective way to recover the gold in short time we use heap leaching, heap leaching is a widely used hydrometallurgical method for extracting gold,the simple process is stockpiling→leaching→carbon absorbtion→smelting, the flowsheet is as below:

 

Simplified-Gold-Recovery-Flowsheet

1.Crushing ore to an appropriate size (not too fine, usually 20–50 mm).

2.Building a heap (pile) of ore on a lined pad to prevent contamination.

3.Spraying or percolating a leaching solution over the heap.

4.Collecting the metal-bearing solution (pregnant solution) at the base.

5.Recovering the metal from the solution, usually via adsorption, precipitation, or electro-winning.

 

Prepare-the-base-pad-gold-heap-leaching

 

Step 1: Prepare the base pad

Usually compact soil or concrete lined with impermeable geomembrane.

Drainage channels are installed to collect leachate.

Step 2: Layer the ore

Place the crushed ore in lifts/layers.

Typical layer thickness: 1–2 meters per lift.

Each layer is slightly compacted and leveled.

Step 3: Build the total heap

Heaps can range in height depending on material and leaching efficiency:

Gold heap leaching: 10–20 meters is common.

Steeper heaps may be unstable; a gentle slope (~30°) is safer.

Step 4: Install irrigation system

Drip or sprinkler system on top of the heap.

Ensures leaching solution percolates evenly through the pile.

 

gold-heap-leaching-process

Heap-Leaching-Process

 

Dasen mining has professional mechanical manufacturing engineers, beneficiation engineers, and a professional equipment installation team and rich practical experience,

Our services include: ore analysis, beneficiation experiment, beneficiation process design, equipment manufacturing, construction, equipment installation, commissioning, operation, and a series of on-site EPC/turn-key production technical services, etc.

Warmly welcome clients from all over the world visiting our factory in China.

 

Whatsapp:+86 133 1927 7356
Email:Desen@oremagnetic.com